Why is Victoria Street closed at Fischer-Hallman again, when work at that intersection began in July 2025 and finished in June? The Region of Waterloo split the project into phases. Phase two started at the same Fischer-Hallman corner and continues in six stages along Victoria and onto Westmount, with the last one scheduled for 2028.
That puts the stretch from Fischer-Hallman Road to Hazelglen Drive at the start of the project. The reopening scheduled for the end of this month is a pause for winter.
The Region's Victoria Street project page covers project 05656, which rebuilds Victoria Street from Fischer-Hallman Road to Lawrence Avenue on a $12,000,000 budget. Phase one ran from July 2025 to June 2026 and covered the Westmount Road and Fischer-Hallman Road intersections along Victoria. The Region says that work is complete.
Phase two, stage 1 runs from Fischer-Hallman to Hazelglen Drive and is scheduled for September to November 2026. On or about November 2, crews moved north between Fischer-Hallman and Fenwick Court and Monte Carlo Street. That section is fully closed to through traffic. Local access to Fenwick Court and Monte Carlo Street is through the Hazelglen Drive intersection.
The Region expects the section to reopen for winter maintenance by the end of November. The City of Kitchener's road closures list shows Victoria Street South closed to through traffic between Fischer-Hallman Road and Hazelglen Drive from November 2 to November 30. The Region notes that weather and changes in scope can affect the timing, so both dates are schedules.
The project has its own text updates. Text VCTA to 57555 to get project news as it is posted. Standard messaging rates apply.
Drivers can follow the detour signs. Bus riders have more to adjust because their stops have moved. Grand River Transit's detour notice for Victoria Street, posted September 17, applies to Route 20. It lists the bus detour for the Fischer-Hallman Road to Hazelglen Drive section as starting Monday, September 28, 2026, and lasting approximately three months. That bus detour began before the full through-traffic closure that started on or about November 2.
These are the stops that are closed and the ones GRT lists to use instead:
| Direction | Closed stops | Alternate stops |
|---|---|---|
| Outbound to Stanley Park | 3142 Victoria/Fischer-Hallman, 3212 Victoria/Monte Carlo | 3170 Fischer-Hallman/Victoria, temporary stop at Highland/Fischer-Hallman, 3214 Hazelglen/Mooregate |
| Inbound to The Boardwalk Station | 3128 Victoria/Fenwick | 3126 Hazelglen/Victoria, temporary stop at Fischer-Hallman/Highland, 3129 Victoria/Fischer-Hallman |
In both directions, the temporary stops are at Highland Road and Fischer-Hallman Road, not on Victoria. For now, the corner many riders use to catch Route 20 has moved south to Highland Road West.
The City's road closures list sends drivers around the closure on Fischer-Hallman, Highland and Westmount roads. That loop runs along roads at Forest Heights' edge, so traffic that would normally use Victoria is on Highland Road West this month.
Two other entries on the same list affect those roads. Fischer-Hallman Road has reduced lanes at Victoria Street from November 2 to November 30. Highland Road West between Ira Needles Boulevard and Trussler Road has utility work from November 2 to December 12. The City lists no lane closures for the Highland work, but crews will be working beside the road for about two weeks after the Victoria closure is scheduled to end.
There is also a new reason to stop along Highland Road West. Goodwill Ontario Great Lakes has opened a donation centre at its new Kitchener Highland Hills location, 875 Highland Rd W, unit 178. Goodwill announced it in early November. The Community Store at the same address is scheduled to open this winter, and Goodwill says the location has created more than 40 jobs in Kitchener. The location's phone number is 519-783-4495.
The closures make more sense once you know what is being built. The Region says the design came out of public feedback and technical review. Public comments were collected from March 26 to April 10, 2024. The finished corridor will include:
For people in Forest Heights, the multi-use paths are the closest part of the plan. They start at Fischer-Hallman, where this fall's stage began, and run toward Westmount. The storm sewer work is the reason the road has to be dug up and closed instead of just repaved.
Phase two's stages don't move down the street in a straight line. After Hazelglen to Westmount, the work moves to the Lawrence Avenue intersection and then back west toward Paulander Drive and Westmount. Here is the Region's published order:
| Stage | Section | Year |
|---|---|---|
| 1 | Fischer-Hallman Road to Hazelglen Drive | 2026 |
| 2 | Hazelglen Drive to Westmount Road | 2027 |
| 3 | Lawrence Avenue and Victoria Street intersection | 2027 |
| 4 | Paulander Drive to Lawrence Avenue | 2027 |
| 5 | Westmount Road West to Paulander Drive | 2027 |
| 6 | Westmount Road West, Vicmount Drive to Victoria Street | 2028 |
The schedule has two consequences for drivers in Forest Heights. Stage 1 is the only stage at the Fischer-Hallman end, so once it is done, the intersection closest to the neighbourhood should be through the heavy work. The next section east, Hazelglen to Westmount, is scheduled for 2027. Anyone who uses Victoria to reach Westmount or go toward Lawrence Avenue will likely meet construction again next year, just further along the street. Stage 6, on Westmount Road West between Vicmount Drive and Victoria Street, is set for 2028. That is three years after phase one began in July 2025.
The Region says it posts schedule updates on its project page as needed, and GRT lists Route 20 changes on its Route 20 alerts page.
Construction like this matters when you're comparing streets, from how close a house sits to a future multi-use path to which intersection you'll use every morning. Ivan's two decades in custom home construction mean we look at what is being built around a home as well as the home itself. If you want to talk through how the Victoria Street work affects a home you own or are considering, The Gascho Group is glad to help. Make your next move with confidence.
Whether you are buying a luxury home, selling an acreage property, relocating within Ontario, or exploring your next investment, I will help you understand the opportunity and make informed decisions at every stage. My approach is personal, strategic, and grounded in honest communication—from our first conversation through negotiation, closing, and beyond. If real estate is part of your next chapter, I would welcome the opportunity to learn what matters most to you and create a plan around it.